Logistic regression analysis for factors influencing cost performance of design-bid-build and design-build projects

View at Publisher Save 10.1108/ecam-07-2015-0119
Abstract
Purpose
The purpose of this paper is to explore the influencing factors of cost performance of design-bid-build (DBB) and design-build (DB) projects and comparing the differences of influencing factors between these two delivery methods.


Design/methodology/approach
This research identified and refined 14 influencing factors through literature review and academic expert discussions. Questionnaire survey was conducted to collect data about the influencing factors and project cost performance. Then those factors were reduced to four components by factor analysis. Logistic regression analysis is used to investigate the relationship between four principal components and project cost performance.


Findings
The results indicate that the significant influencing factors of project cost performance of DBB projects and DB projects are different. For DBB projects, owner abilities, such as owner team ability, owner experience, and owner finance, are important influencing factors causing cost overruns, while for DB projects cost performance is more sensitive to the contractor abilities, namely, contractor team ability, contractor finance, contractor experience, etc.


Research limitations/implications
The results of the paper are mainly derived by quantitative research method based on the survey of 144 samples, so the results may need validation by qualitative studies. Further research could apply case study or interview to validate the findings in this research. In addition, project type and location are not considered as control variables due to the limited number of samples, future research could be conducted to investigate their relationship with project performance.


Practical implications
The findings of this research not only help practitioners have a better understanding of the factors influencing project cost performance, but also provide some guidelines for practitioners to pay attention to different factors to better control the cost performance within different delivery systems.


Originality/value
Owner ability and contractor ability are found to be of different importance in influencing cost performance of DBB and DB projects. This research extends previous research on cost management by considering different significant factors in influencing project cost performance within DBB and DB projects.
Topics

No keywords indexed for this article. Browse by subject →

References
79
[1]
"Factors affecting contractors’ risk of cost overburden" Journal of Management in Engineering (1998) 10.1061/(asce)0742-597x(1998)14:1(67)
[2]
"Selecting the appropriate project delivery method using AHP" International Journal of Project Management (2002) 10.1016/s0263-7863(01)00032-1
[3]
"Factors causing project cost overrun in the telecommunications industry in Oman" International Journal of Information Technology Project Management (2014) 10.4018/ijitpm.2014070105
[4]
"Significant factors causing cost overruns in telecommunication projects in Nigeria" Journal of Construction in Developing Countries (2010)
[5]
"Assessing the corporate service quality performance of design-build contractors using quality function deployment" Construction Management and Economics (2003) 10.1080/0144619032000079716
[6]
"Cost overruns in public projects" International Journal of Project Management (1985) 10.1016/0263-7863(85)90053-5
[7]
"Predicting cost deviation in reconstruction projects: artificial neutral networks versus regression" Journal of Construction Engineering and Management (2003) 10.1061/(asce)0733-9364(2003)129:4(405)
[8]
"Modelling global risk factors affecting construction cost performance" International Journal of Project Management (2003) 10.1016/s0263-7863(02)00017-0
[9]
"Geographical variation in project cost performance: the Netherlands versus worldwide" Journal of Transport Geography (2012)
[10]
"Different cost performance: different determinants? The case of cost overruns in Dutch transport infrastructure projects" Transport Policy (2012)
[11]
(1978)
[12]
"Predicting project cost performance level by assessing risk factors of building construction in South Korea" Journal of Asian Architecture and Building Engineering (2011) 10.3130/jaabe.10.437
[13]
"Causes of delays and overruns of construction projects in developing countries" (1984)
[14]
"Factors affecting the success of a construction project" Journal of Construction Engineering and Management (2004) 10.1061/(asce)0733-9364(2004)130:1(153)
[15]
"Design and build project success factors: multivariate analysis" Journal of Construction Engineering and Management (2001) 10.1061/(asce)0733-9364(2001)127:2(93)
[16]
"Reasons for cost and schedule increase for engineering design projects" Journal of Management in Engineering (2002) 10.1061/(asce)0742-597x(2002)18:1(29)
[17]
"Analysis of project delivery systems in Chinese construction industry with data envelopment analysis (DEA)" Engineering Construction and Architectural Management (2010) 10.1108/09699981011090215
[18]
"Interrelationships among critical success factors of construction projects based on the structural equation model" Journal of Management in Engineering (2012) 10.1061/(asce)me.1943-5479.0000104
[19]
"An exploration into cost-influencing factors on construction projects" International Journal of Project Management (2014) 10.1016/j.ijproman.2013.10.003
[20]
"Exploring the potential for predicting project dispute resolution satisfaction using logistic regression" Journal of Construction Engineering and Management (2010) 10.1061/(asce)co.1943-7862.0000157
[21]
"Evaluation of risk factors leading to cost overrun in delivery of highway construction projects" Journal of Construction Engineering and Management (2010) 10.1061/(asce)co.1943-7862.0000160
[22]
Exploratory Factor Analysis With Small Sample Sizes

J. C. F. de Winter*, D. Dodou*, P. A. Wieringa

Multivariate Behavioral Research 2009 10.1080/00273170902794206
[23]
"Evaluation of factors affecting time and cost performance in Hong Kong building projects" Engineering Construction and Architectural Management (1999) 10.1108/eb021119
[24]
"Cost overruns and failure in project management: understanding the roles of key stakeholders in construction projects" Journal of Construction Engineering and Management (2013) 10.1061/(asce)co.1943-7862.0000621
[25]
"Understanding stakeholders’ perspective of cost estimation in project management" International Journal of Project Management (2011) 10.1016/j.ijproman.2010.06.001
[26]
FACTORS AFFECTING THE PERFORMANCE OF CONSTRUCTION PROJECTS IN THE GAZA STRIP

Adnan Enshassi, Sherif Mohamed, Saleh Abushaban

JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT 2009 10.3846/1392-3730.2009.15.269-280
[27]
"Curbing optimism bias and strategic misrepresentation in planning: reference class forecasting in practice" European Planning Studies (2008) 10.1080/09654310701747936
[28]
How common and how large are cost overruns in transport infrastructure projects?

Bent Flyvbjerg, Mette K. Skamris Holm, Søren L. Buhl

Transport Reviews 2003 10.1080/01441640309904
[29]
"Framing of project critical success factors by a systems model" International Journal of Project Management (2006) 10.1016/j.ijproman.2005.07.004
[30]
"Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study" International Journal of Project Management (2003) 10.1016/s0263-7863(02)00055-8
[31]
"Measurement model quality, sample size, and solution propriety in confirmation factor models" Multivariate Behavioral Research (2006) 10.1207/s15327906mbr4101_5
[32]
"The influence of procurement methods on project performance: a conceptual framework" (2000)
[33]
"Relating cost growth from the initial estimate to design fee for transportation projects" Journal of Construction Engineering and Management (2007) 10.1061/(asce)0733-9364(2007)133:6(404)
[34]
(1995)
[35]
(1979)
[36]
"Empirical comparison of design/build and design/bid/build project delivery methods" Journal of Construction Engineering and Management (2009) 10.1061/(asce)co.1943-7862.0000017
[37]
"Capital project performance measurement and benchmarking in Singapore" Engineering Construction and Architectural Management (2013) 10.1108/09699981311303017
[38]
"Factors affecting cost performance: evidence from Indian construction projects" International Journal of Project Management (2005) 10.1016/j.ijproman.2004.10.003
[39]
"Factors influencing construction time and cost overruns on high-rise projects in Indonesia" Construction Management and Economics (1997) 10.1080/014461997373132
[40]
"Discriminant analysis for predicting ranges of cost variance in international construction projects" Journal of Construction Engineering and Management (2008) 10.1061/(asce)0733-9364(2008)134:6(398)
[41]
Comparison of U.S. Project Delivery Systems

Mark Konchar, Victor Sanvido

Journal of Construction Engineering and Management 1998 10.1061/(asce)0733-9364(1998)124:6(435)
[42]
"Determinants of successful design-build projects" Journal of Construction Engineering and Management (2008) 10.1061/(asce)0733-9364(2008)134:5(333)
[43]
"Cost overrun and cause in Korean social overhead capital projects: roads, rails, airports and ports" Journal of Urban Planning and Development (2008) 10.1061/(asce)0733-9488(2008)134:2(59)
[44]
"Explaining cost overruns in infrastructure projects: a new framework with applications to Sweden" Construction Management and Economics (2015) 10.1080/01446193.2015.1064983
[45]
"Predicting performance of design-build and design-bid-build projects" Journal of Construction Engineering and Management (2004) 10.1061/(asce)0733-9364(2004)130:1(75)
[46]
"Comparing the performance of design-build and design-bid-build building projects in Singapore" Architectural Science Review (2004) 10.1080/00038628.2004.9697040
[47]
"Determining the probability of project cost overruns" Journal of Construction Engineering and Management (2013) 10.1061/(asce)co.1943-7862.0000575
[48]
"A logistic regression approach to modeling the contractor’s decision to bid" Construction Management and Economics (2004) 10.1080/01446190310001649056
[49]
Sample size in factor analysis.

Robert C. MacCallum, Keith F. Widaman, Shaobo Zhang et al.

Psychological Methods 1999 10.1037/1082-989x.4.1.84
[50]
"Project delivery system under uncertainty: multilevel decision aid model" Journal of Management in Engineering (2007) 10.1061/(asce)0742-597x(2007)23:4(200)

Showing 50 of 79 references

Cited By
25
Metrics
25
Citations
79
References
Details
Published
Jan 16, 2017
Vol/Issue
24(1)
Pages
118-132
License
View
Cite This Article
Wenxue Lu, YuanYuan Hua, Sujuan Zhang (2017). Logistic regression analysis for factors influencing cost performance of design-bid-build and design-build projects. Engineering, Construction and Architectural Management, 24(1), 118-132. https://doi.org/10.1108/ecam-07-2015-0119